Road Closure at the level crossing in Fulbourn, Station Road
Cadent Gas have provided an update on their work in Fulbourn: they are now projecting that the work will finish in the week of 6th-9th May. This is well head of the scheduled date of 13th June. It is a projection, but all being well the road to Fulbourn should be open from 12th May. I am sure there will be an update nearer the time.
Claire Daunton, County Councillor